Sprint Timeline
- Sprint 1 (Study and Architecture) - 13 October 2025 to 3 November 2025
- Sprint 2 (Initial MVP & Elaboration) - 4 November 2025 to 23 November 2025
- Sprint 3 (Final MVP) - 24 November 2025 to 15 December 2025
- Sprint 4 (Improve MVP) - 9 February 2026 to 8 March 2026
- Sprint 5 (Initiate Final System) - 9 March 2026 to 6 April 2026
- Sprint 6 (Improve Final System) - 7 April 2026 to 28 April 2026
- Sprint 7 (Technical and Risk Assessment) - 29 April 2026 to 20 May 2026